Executive Lead Member for Universal Services Decision Day & Executive Member for Highways and Waste Decision Day - Hampshire
Meeting Times
Scheduled Time
Start:
Monday, 3rd March 2025
2:00 PM
Monday, 3rd March 2025
2:00 PM
End:
Monday, 3rd March 2025
6:00 PM
Monday, 3rd March 2025
6:00 PM
Meeting Status
Status:
Confirmed
Confirmed
Date:
03 Mar 2025
03 Mar 2025
Location:
Remote Decision Day - Remote
Remote Decision Day - Remote
Meeting Attendees
Agenda
0
Exclusion of the Press and Public
That the public be excluded from the meeting during the following item of business, as it is likely, in view of the nature of the business to be transacted or the nature of the proceedings, that if members of the public were present during this item there would be disclosure to them of exempt information within Paragraph 3 of Part 1 of Schedule 12A to the Local Government Act 1972, and further that in all the circumstances of the case, the public interest in maintaining the exemption outweighs the public interest in disclosing the information, for the reasons set out in the report.
0
Deputations
To receive any deputations notified under Standing Order 12.
0
KEY DECISIONS (NON-EXEMPT/NON-CONFIDENTIAL)
0
NON KEY DECISIONS (NON-EXEMPT/NON-CONFIDENTIAL)
0
0
Executive Member for Highways and Waste
0
Deputations
To receive any deputations notified under Standing Order 12.
0
NON KEY DECISIONS (NON-EXEMPT/NON-CONFIDENTIAL)
0
Executive Lead Member for Universal Services
0
KEY DECISIONS (EXEMPT/CONFIDENTIAL)
1
Project Appraisal - A27 Segensworth Walking and Cycling Improvements
To consider a report of the Director of Universal Services regarding the proposed A27 Segensworth Walking/ Cycling Link scheme and seeking approval to progress and implement this scheme.
Attachments:
- Document PA - A27 Segensworth Walking and Cycling Improvements 21 Feb 2025
- Document Decision Record 04 Mar 2025
Minutes
2
Project Appraisal - Havant Footbridge Replacement - Contractor Engagement Stage 1
To consider a report of the Director of Universal Services regarding a replacement footbridge over the railway adjacent to Havant Station and seeking approval to appoint a contractor experienced in working within the rail environment.
Attachments:
- Document Outline PA - Havant Footbridge Replacement - Contractor Engagement Stage 21 Feb 2025
- Document Decision Record 04 Mar 2025
Minutes
3
Spend Approval Future Property Term Maintenance Contract
To consider a report of the Director of Universal Services regarding a new contract for the delivery of engineering and building fabric reactive work and engineering planned preventative maintenance across the Hampshire County Council (HCC) and Service Level Agreement (SLA) schools’ estate.
Attachments:
- Document Spend Approval Property Term Maintenance Contract 21 Feb 2025
- Document Decision Record 04 Mar 2025
Minutes
4
Repairs to the Chapel Tower Royal Victoria Country Park Netley
To consider a report of the Director of Universal Services regarding the proposals for the protection and repair of the Chapel Tower at Royal Victoria Country Park.
Attachments:
- Document Repairs to the Chapel Tower Royal Victoria Country Park Netley 21 Feb 2025
- Document Decision Record 04 Mar 2025
Minutes
5
Basingstoke Canal Annual Update
To consider a report of the Director of Corporate Operations regarding an update on the Basingstoke Canal Authority partnership and seeking approval of the 2023/24 final outturn, the 2024/25 revised budget and the 2025/26 forward budget and scheme of charges.
Attachments:
- Document Basingstoke Canal Annual Update and Budget 21 Feb 2025
- Document Decision Record 04 Mar 2025
Minutes
6
Property Services Asset Decisions
To consider a report of the Director of Universal Services regarding a number of formal transactions relating to Hampshire County Council owned or occupied assets.
Attachments:
- Document CONFIDENTIAL - Property Services Asset Decisions 21 Feb 2025
- Document CONFIDENTIAL - Property Services Asset Decisions - Appendix 21 Feb 2025
- Document Decision Record 04 Mar 2025
Minutes
7
Project Appraisal - A3090 Halterworth Lane Improvements Romsey
To consider a report of the Director of Universal Services regarding the proposals for pedestrian and cycling accessibility improvements along the A3090 Winchester Road at its junction with Halterworth Lane linking to future improvements which are currently being developed for the A3090 Winchester Road corridor.
Attachments:
- Document PA - A3090 Halterworth Lane Improvements Romsey 21 Feb 2025
- Document Decision Record 04 Mar 2025
Minutes
8
Project Appraisal - Andover: A343 Newbury Road Footway & Smannell Road Roundabout Improvements
To consider a report of the Director of Universal Services regarding proposals for highway and footway improvements on the A343 and at Smannell Road Roundabout in Andover.
Attachments:
- Document PA - Andover - A343 Newbury Road footway & Smannell Road Roundabout Improvements 21 Feb 2025
- Document Decision Record 04 Mar 2025
Minutes
9
Future Ownership and Maintenance of Bus Shelters - Expansion
To consider a report of the Director of Universal Services regarding authority to increase the previous cost value for the provision and maintenance of the new bus shelters that Hampshire County Council has taken ownership of from other borough and districts, up to a value of £500,000 per annum, to be able to cover any new areas added across Hampshire.
Attachments:
- Document Future Ownership and Maintenance of Bus Shelters – Expansion 21 Feb 2025
- Document Decision Record 04 Mar 2025
Minutes
Previous Meetings
Join the Discussion
You need to be signed in to comment.
Sign in