This is a meeting of the Housing Board of Gosport Borough Council held on the 27th Sep 2023.
The last meeting was on 5th Mar 2025. The next meeting is scheduled for 11th Jun 2025.
Council Chamber
No recordings have been submitted for this meeting yet. If you have one, you can Upload a Recording
Item | Title | Minutes |
1 | APOLOGIES FOR NON ATTENDANCE |
There were none |
2 | DECLARATIONS OF INTEREST |
There were none |
3 | MINUTES OF THE PREVIOUS MEETINGS OF THE HOUSING BOARD HELD ON 23 NOVEMBER 2022 &25 JANUARY 2023 |
Minutes Public Pack, 23/11/2022 Housing Board
Minutes Public Pack, 25/01/2023 Housing Board RESOLVED: That the minutes of the meetings held on 23 November 2022 and25th January 2023 were signed as a true and correct record. |
4 | DEPUTATIONS - STANDING ORDER 3.4 |
There were none |
5 | PUBLIC QUESTIONS |
There were none |
6 | Housing Development Update |
Report for Housing Board 270923 2
Consideration was given to a report by the Head of Housing setting out the tender process to procure a construction contractor to deliver the new social housing on sites at Stoners Close, Wheelers Close and Glebe Drive.
The Head of Housing advised Members that the team had been working on this project constantly, but the processes of procurement, identifying the criteria at all sites and especially planning considerations had taken many months. Now that initial work had taken place, there is a clear timetable and things should be able to move quickly.
Members were advised that the Expression of Interest process had yielded a number of responses, so there was confidence that there would be interested parties submitting tenders.
RESOLVED: That the Board noted the process to procure a construction contractor using the National Framework Partnership. |
7 | ANY OTHER ITEMS |
|
None
Expected
5th Mar 2025 Cancelled
Housing Board
20th Nov 2024 Cancelled
Housing Board
6th Mar 2024 Cancelled
Housing Board
22nd Nov 2023 Cancelled
Housing Board
14th Jun 2023 Cancelled
Housing Board