Meeting
Housing Overview and Scrutiny Panel - New Forest
Scheduled Time
Wednesday, 20th January 2021
6:00 PM
Wednesday, 20th January 2021
10:00 PM
Actual Time
Wednesday, 20th January 2021
12:00 AM
Wednesday, 20th January 2021
12:00 AM
Confirmed
20 Jan 2021
Microsoft Teams - Online
Cllr Ann Sevier
Present, as expected
Cllr Anne Corbridge
Apologies
Cllr Andrew Gossage
Present, as expected
Cllr Joshua Kidd
Present, as expected
Brian Byrne
In attendance
Tim Davis
In attendance
Richard Fudge
In attendance
Kevin Green
In attendance
Richard Knott
In attendance
Grainne O'Rourke
In attendance
Daniel Reynafarje
In attendance
Ritchie Thomson
In attendance
Karen Wardle
In attendance
Cllr Diane Andrews
In attendance
Cllr Ann Bellows
In attendance
Cllr Sue Bennison
In attendance
Cllr Martyn Levitt
In attendance
That the minutes of the meeting held on 12 November 2020 be signed by the Chairman as a correct record.
Members are asked to discuss any possible interests with Democratic Services prior to the meeting.
- Document HRA Budget RPT 12 Jan 2021
- Document Appendix 1 12 Jan 2021
- Document Appendix 2 12 Jan 2021
- Document Appendix 3 12 Jan 2021
It was noted that the budget proposed a social rent increase of 1.5%, in line with the recommendation from Government. This would be the second annual increase in social rents, following a four-year period where the social rents were reduced annually (by 1% each year). Service charges were proposed to have an inflationary increase of 0.5% and a review of service charges would be carried out in 2021/22. There would be no change to garage rents. The estimated HRA income for 2021/22 was noted to be £873,000 higher than the original budget for 2020/21.
The HRA expenditure budget for 2021/22 was proposed to be increased, and within this there would be an additional £647,000 in resources available for the capital development programme, which supported the Housing Strategy.
Views on the report had been received from the Tenant Involvement Group (TIG) and it was noted that the TIG recognised the fact that maintenance costs increase over time. The Tenant Representatives felt that the proposals were appropriate and sensible and supported the proposals within the HRA budget and the capital expenditure programme for 2021/22.
Support was expressed regarding the proposed social rent increase in recognition of the need to continue to maintain homes to the decent homes standard and that the stock condition survey had identified improvements which needed to be made to the Council’s housing stock. An alternative view was expressed by two members of the Panel who felt that the social rents should be frozen for a year, and that the proposed rise to social rents would negatively impact those tenants who were currently struggling in the coronavirus pandemic.
The planned maintenance and improvement programme was noted. Members questioned the increase in budget for miscellaneous works, over the three year period. This had been identified as part of the continuous improvements to the Council’s housing stock and the acceleration of the programme of works arising from the stock condition survey. It was anticipated that additional unplanned works could arise whilst other improvement works were being carried out.
£500,000 had been identified in the capital programme for 2021/22 Greener Housing Initiatives. The Council had bid for Government funding of £280,000 towards the provision of air source heat pumps on some of the Council’s more rural properties and those which were ‘off gas’. Those who were in fuel poverty with an annual income of less than £30,000 were specifically targeted.
RESOLVED:
That the Housing Revenue Account budget and Housing Public Sector Capital Expenditure Programme 2021/22 be noted and supported.
- Document Telecare Presentation 26 Feb 2021
The Council’s Housing Service provided a number of door entry, fire alarm monitoring and alarm services for housing stock across the District, as well as providing the Appletree Careline service to approximately 2,000 people. The buildings which were monitored included communal or shared access properties which primarily accommodated age restricted or more vulnerable homeless clients.
The current services rely on analogue technology. Nationally, BT had announced they would switch off the analogue system in 2025 and that future delivery of services would need to be made over a digital network. This was the main driver for change as this would render all existing analogue solutions incompatible with a new digital network, rendering the current system inoperable from 2025.
In addition, NFDC’s hardware infrastructure in its housing blocks had become outdated and was no longer cost effective in terms of repairs and investment. When faults occurred, it was becoming increasingly common that parts were no longer available or extremely hard to obtain. This was not sustainable for the future.
The Panel noted that these monitoring services could currently only be provided from within Appletree Court, however the coronavirus pandemic had demonstrated the need to provide resilience and increase the operational ability of delivering Careline and monitoring services remotely, were required.
A system was therefore needed which would be robust and fit for the future. A programme of work had been identified which included the replacement of the current systems across the Council’s housing stock in order to be digitally compliant by 2025. Bridging software and hardware, converting analogue to digital, would be procured to allow the continuing use of existing monitoring units in customers’ home, up to their normal operating life, which would provide significant cost savings. Whilst there was a cost associated with the replacement of the telecare infrastructure, there would be future savings in relation to maintenance by removing the expensive and outdated equipment.
The Panel noted the work proposed to be carried out over the next financial year and beyond. The Panel acknowledged the importance of the need to replace the ageing infrastructure. A procurement exercise would be carried out, and following appointment of a supplier, implementation would commence as soon as it would possible to do so within the following the 2021/22 financial year.
The Panel expressed their support to the replacement of the telecare infrastructure and requested that an update be provided to the meeting in September 2021.
- Document Homelessness Update Presentation 26 Feb 2021
It was noted that the new housing allocation system had been launched a year ago, which managed all applications online, including the bidding for properties. There were currently 1,239 live applications. 245 applicants had been rehoused since January 2020 across all four housing allocation bands.
There were currently 12 rough sleepers in the District, of which five had firm accommodation plans. Some of the rough sleepers had declined offers of support but officers would still work to support them.
The Panel noted that 154 households had been provided with emergency accommodation since 1 March 2020 and that 50 householders were currently in external temporary accommodation. It was expected that more Council owned temporary accommodation would become available during 2021/22 to reduce the need for use of external B&B; accommodation.
Officers were meeting fortnightly with MHCLG advisors to discuss additional funding options, specialist roles and prevention activities in relation to homelessness.
Members questioned the number of rough sleepers recorded in recent months compared with other months. It was noted that in March 2020 the District Council accommodated 35 rough sleepers, however, in general there were circa 10-12 each at any one time. It was acknowledged that 22 rough sleepers had been recorded in November 2020, however this had been addressed quickly by the homelessness team.
- Document Dev update Presentation 26 Feb 2021
There were various projects for refurbishment and temporary accommodation. It was anticipated that the Heather Road scheme in Blackfield would provide five units of shared accommodation and would be ready for occupation in March.
In relation to the Council’s new build properties, two units of shared ownership had been marketed at Mulberry Close in Blackfield and a positive response had been received in relation to these. The Panel noted the proposals for redevelopment of Testwood Social Club to provide low carbon housing, to be built to the Future Homes Standard.
It was anticipated that around 200 additional affordable homes would have completed by the end of the financial year. Taking these and other speculative opportunities into account, the present potential pipeline stood at 473 affordable homes, albeit made up from openings at different stages and with varying degrees of certainty.
She highlighted and praised the work of the housing maintenance team. Essential maintenance works and repairs continued to take place in order for tenants to have homes which were safe and warm. Void properties continued to be relet.
Operational staff were working to the highest hygiene standards, observing social distancing when entering tenants’ properties wearing face coverings to give the tenant reassurance and in order to keep members of staff safe from the risk of coronavirus.
She praised the housing officers for doing all they could to maintain excellent services and invited the support of the Panel in thanking them.
- Document Housing Work Programme 12 Jan 2021
- Document Housing Portfolio Performance Dashboard 12 Jan 2021
RESOLVED:
That the work programme be agreed with the inclusion of the telecare infrastructure replacement project to the meeting in September 2021.
Join the Discussion
You need to be signed in to comment.
Sign in