Havant Borough Council
Councillors:
36
Wards:
17
Committees:
35
Meetings (2025):
89
Meetings (2024):
96
Meeting
Site Viewing Working Party - Havant
Meeting Times
Scheduled Time
Start:
Thursday, 24th October 2024
1:00 PM
Thursday, 24th October 2024
1:00 PM
End:
Thursday, 24th October 2024
5:00 PM
Thursday, 24th October 2024
5:00 PM
Meeting Status
Status:
Confirmed
Confirmed
Date:
24 Oct 2024
24 Oct 2024
Location:
Meeting Attendees

Vice-Chairman
Vice Chairman of Planning Committee
Secretary
Democratic Services Officer
Ernest Lam
Present, as expected
Secretary
Democratic Services Officer
Mark Gregory
Expected
Officer
Development Manager
Steve Weaver
Present, as expected
Public
Spare Copies
Expected

Committee Member
Chairman of Overview and Scrutiny Committee

Chairman
Cabinet Lead for Planning and Environment and Chairman of Planning Committee
Officer
Planning Consultant
Narinder Lakhan
Present, as expected
Secretary
Democratic Services Officer
Lauren Maidens
Present, as expected

Committee Member
Deputy Mayor of the Council and Vice Chairman of Licensing Committee

Committee Member
Chairman of Licensing Committee

Committee Member
Cabinet Lead for Climate Emergency, Environment & Water Quality (Climate Change Champion)

Committee Member
Councillor Elizabeth Lloyd (formerly known as Dianne)
Independent for Stakes
Present, as expected
View Profile
Committee Member
Leader of the Green Party & Cabinet Lead Commercial
Agenda
1
Apologies
To receive and record any apologies for absence.
Minutes
Apologies for absence were received from Councillors Robert and Shimbart.
2
Declarations of Interests
To receive and record any declarations of interests from Members present.
Minutes
There were no declarations of interests relating to matters on the agenda.
3
Site Visits
3
APP/24/00312 - Havant Thicket, adjacent to Sir George Staunton Country Park, Middle Park Way, Havant
Proposal: Application under Section 73 of the Town and Country Planning Act 1990 in respect of Conditions 2 and 3 of the Hybrid permission planning reference APP/20/00990 dated 15th October 2021 for proposed changes to the size and alignment of the main reservoir embankment.
(For Committee papers and reports see agenda for the Planning Committee to be held on the 31 October 2024)
(For Committee papers and reports see agenda for the Planning Committee to be held on the 31 October 2024)
Minutes
Proposal: Application under Section 73 of the Town and Country Planning Act 1990 in respect of Conditions 2 and 3 of the Hybrid permission planning reference APP/20/00990 dated 15th October 2021 for proposed changes to the size and alignment of the main reservoir embankment.
The site was viewed at the request of the Executive Head of Place.
The Working Party received a report by the Executive Head of Place.
The Working Party was accompanied around the site by the applicant’s agent and representatives of the applicant, who were available to answer any factual or technical questions.
The Working Party viewed the site, the subject of the application, to assess whether there were any additional matters that should be considered by the Planning Committee.
In addition to viewing the application site, the Working Party also viewed the site from the Swanmore Road Compound.
RESOLVED that, based on the site inspection and information available at the time, the following additional information be provided to the Planning Committee:
(a) the reasons behind the change to the angle of the embankment slope;
(b) how the change in angle will affect the engineering capabilities of building the control house and how much of it will be visible;
(c) clarification on why the maximum capacity of the reservoir remains unchanged despite the changes to the reservoir’s embankment;
(d) what other options were considered in respect of the relocation of the valve tower, and reasons why these were dismissed; and
(e) further details regarding the respective risk assessments and mitigations relating to the original siting of the tower, and the now proposed site in the water.
The site was viewed at the request of the Executive Head of Place.
The Working Party received a report by the Executive Head of Place.
The Working Party was accompanied around the site by the applicant’s agent and representatives of the applicant, who were available to answer any factual or technical questions.
The Working Party viewed the site, the subject of the application, to assess whether there were any additional matters that should be considered by the Planning Committee.
In addition to viewing the application site, the Working Party also viewed the site from the Swanmore Road Compound.
RESOLVED that, based on the site inspection and information available at the time, the following additional information be provided to the Planning Committee:
(a) the reasons behind the change to the angle of the embankment slope;
(b) how the change in angle will affect the engineering capabilities of building the control house and how much of it will be visible;
(c) clarification on why the maximum capacity of the reservoir remains unchanged despite the changes to the reservoir’s embankment;
(d) what other options were considered in respect of the relocation of the valve tower, and reasons why these were dismissed; and
(e) further details regarding the respective risk assessments and mitigations relating to the original siting of the tower, and the now proposed site in the water.
3
APP/24/00311 - Havant Thicket, adjacent to Sir George Staunton Country Park, Middle Park Way, Havant
Proposal: Application for approval of all Reserved Matters (siting, scale, external appearance and landscaping) relating to Phase 3 (Main Embankment) of the Thicket Reservoir development pursuant to condition 2 of the Hybrid permission planning reference APP/20/00990 dated 15th October 2021.
(For Committee papers and reports see agenda for the Planning Committee to be held on the 31 October 2024)
(For Committee papers and reports see agenda for the Planning Committee to be held on the 31 October 2024)
Minutes
Proposal: Application for approval of all Reserved Matters (siting, scale, external appearance and landscaping) relating to Phase 3 (Main Embankment) of the Thicket Reservoir development pursuant to condition 2 of the Hybrid permission planning reference APP/20/00990 dated 15th October 2021 (as recommended to be amended by S73 Application APP/24/00312).
The site was viewed at the request of the Executive Head of Place.
The Working Party received a report by the Executive Head of Place.
The Working Party was accompanied around the site by the applicant’s agent and representatives of the applicant, who were available to answer any factual or technical questions.
The Working Party viewed the site, the subject of the application, to assess whether there were any additional matters that should be considered by the Planning Committee.
In addition to viewing the application site, the Working Party also viewed the site from Swanmore Road Compound.
RESOLVED that, based on the site inspection and information available at the time, the following additional information be provided to the Planning Committee:
(a) the reasons behind the change to the angle of the embankment slope
(b) how the change in angle will affect the engineering capabilities of building the control house and how much of it will be visible
(c) clarification on why the maximum capacity remains unchanged despite the changes to the reservoir’s embankment
(d) reasons and options considered behind the relocation of the valve tower
(e) whether new risk assessments have been carried out for the proposed amendments
The site was viewed at the request of the Executive Head of Place.
The Working Party received a report by the Executive Head of Place.
The Working Party was accompanied around the site by the applicant’s agent and representatives of the applicant, who were available to answer any factual or technical questions.
The Working Party viewed the site, the subject of the application, to assess whether there were any additional matters that should be considered by the Planning Committee.
In addition to viewing the application site, the Working Party also viewed the site from Swanmore Road Compound.
RESOLVED that, based on the site inspection and information available at the time, the following additional information be provided to the Planning Committee:
(a) the reasons behind the change to the angle of the embankment slope
(b) how the change in angle will affect the engineering capabilities of building the control house and how much of it will be visible
(c) clarification on why the maximum capacity remains unchanged despite the changes to the reservoir’s embankment
(d) reasons and options considered behind the relocation of the valve tower
(e) whether new risk assessments have been carried out for the proposed amendments