Gosport Borough Council
Councillors:
28
Wards:
14
Committees:
10
Meetings (2025):
50
Meetings (2024):
47
Meeting
Community & Environment Board - Gosport
Meeting Times
Scheduled Time
Start:
Wednesday, 21st June 2023
6:00 PM
Wednesday, 21st June 2023
6:00 PM
End:
Wednesday, 21st June 2023
10:00 PM
Wednesday, 21st June 2023
10:00 PM
Actual Time
Started:
Wednesday, 21st June 2023
12:00 AM
Wednesday, 21st June 2023
12:00 AM
Finished:
Wednesday, 21st June 2023
10:27 PM
Wednesday, 21st June 2023
10:27 PM
Meeting Status
Status:
Confirmed
Confirmed
Date:
21 Jun 2023
21 Jun 2023
Location:
Council Chamber
Council Chamber
Meeting Attendees
Committee Member
Committee Member
Committee Member
Agenda
1
Apologies for non-attendance
Minutes
Apologies were received from:
Councillor Huggins, who was substituted by Councillor Burgess
Councillor Maynard who was substituted by Councillor Cox
Councillor Johnston who was substituted by Councillor Earle
Councillor Huggins, who was substituted by Councillor Burgess
Councillor Maynard who was substituted by Councillor Cox
Councillor Johnston who was substituted by Councillor Earle
2
Declarations of interest
Minutes
There were none
3
Minutes of the meeting of the board held on 1st March 2023
Attachments:
- Document Minutes Public Pack, 01/03/2023 Community & Environment Board 13 Jun 2023
Minutes
RESOLVED: That the minutes of the previous meeting held on the 1 March 2023 were signed as a true and correct record.
4
Deputations- Standing Order 3.4
(NOTE: The Board is required to receive a deputation(s) on a matter which is before the meeting of the Board provided that notice of the intended deputation and its object shall have been received by the Borough Solicitor by 19 June 2023. The total time for deputations in favour and against a proposal shall not exceed 10 minutes)
Minutes
There were none
5
Public Questions- Standing order 3.5
(NOTE: The Board is required to allow a total of 15 minutes for questions from Members of the public on matters within the terms of reference of the Board provided that notice of such Question(s) shall have been submitted to the Borough Solicitor by 12 noon on 19 June 2023)
Minutes
There were none
6
Construction of Flood Defence Structures at Forton
Attachments:
- Document Forton CE May'23_v3.5 13 Jun 2023
Minutes
Consideration was given to a report by the Chief Executive updating members on the progress with the Forton coastal defence scheme since the update in March 2023 and seeking approval for the project delivery.
Members were reminded of the funding received to date and advised that a decision on the inflation claim should be known by the end of the week, which if successful, would close the funding gap.
Officers advised that the design work was on target, with remaining work to finalise the drawings, including revisions to mitigate the badger issue. The planning application would be submitted once the designs were completed, with a target of the Autumn Regulatory Board. The tender process is anticipated to start in July 2023.
Members were advised that the April 2024 start date was the earliest possible start date due to over wintering of birds. The window available for work in the badger area was July to November, making the period of April to November the optimal timeframe for the project.
In answer to a Member’s question, Officers agreed to provide more details and assessment of the effect of flooding beyond the number of properties mentioned in the report. Flood modelling and the number of properties affected, underpins the eligibility and amount of potential Environment Agency funding, but there would also be impact on highways, vehicles, infrastructure, and risk to life.
Officers advised that their engineering experience and information in previous tenders showed that the project was deliverable in the time frame available. They agreed that there are always unknown issues that might arise once on site, but the team have been managing the risks getting the project to site, and have carried out full due diligence and trial pits for below ground risks.
In answer to a Member’s question, Officers advised that the badgers had not been picked up on the initial environmental surveys as they were later found to be located beneath a building with no obvious signs of a sett. Sett re-location had been considered but ruled out as high risk option when compared to the chosen option of relocating the defence away from the sett.
Officers advised that the Environment Agency had indicated a high confidence that the inflation claim will be approved, and that the time needed for the assessment was due to the necessary due diligence applied to what is a relatively new funding mechanism.
Members were advised that the funding achieved to date is ring fenced and cannot be moved to another project.
RESOLVED: That the Board approved that:
· Authority is given to the Chief Executive:
a) To undertake the procurement of the works and the evaluation of bids received, and
b) In consultation with the section 151 officer, to award a contract for the works to the preferred bidder, subject to sufficient funding being in place.
· The project team report back to Board with a project update in Autumn 2023 to confirm the expected start date of April 2024.
Members were reminded of the funding received to date and advised that a decision on the inflation claim should be known by the end of the week, which if successful, would close the funding gap.
Officers advised that the design work was on target, with remaining work to finalise the drawings, including revisions to mitigate the badger issue. The planning application would be submitted once the designs were completed, with a target of the Autumn Regulatory Board. The tender process is anticipated to start in July 2023.
Members were advised that the April 2024 start date was the earliest possible start date due to over wintering of birds. The window available for work in the badger area was July to November, making the period of April to November the optimal timeframe for the project.
In answer to a Member’s question, Officers agreed to provide more details and assessment of the effect of flooding beyond the number of properties mentioned in the report. Flood modelling and the number of properties affected, underpins the eligibility and amount of potential Environment Agency funding, but there would also be impact on highways, vehicles, infrastructure, and risk to life.
Officers advised that their engineering experience and information in previous tenders showed that the project was deliverable in the time frame available. They agreed that there are always unknown issues that might arise once on site, but the team have been managing the risks getting the project to site, and have carried out full due diligence and trial pits for below ground risks.
In answer to a Member’s question, Officers advised that the badgers had not been picked up on the initial environmental surveys as they were later found to be located beneath a building with no obvious signs of a sett. Sett re-location had been considered but ruled out as high risk option when compared to the chosen option of relocating the defence away from the sett.
Officers advised that the Environment Agency had indicated a high confidence that the inflation claim will be approved, and that the time needed for the assessment was due to the necessary due diligence applied to what is a relatively new funding mechanism.
Members were advised that the funding achieved to date is ring fenced and cannot be moved to another project.
RESOLVED: That the Board approved that:
· Authority is given to the Chief Executive:
a) To undertake the procurement of the works and the evaluation of bids received, and
b) In consultation with the section 151 officer, to award a contract for the works to the preferred bidder, subject to sufficient funding being in place.
· The project team report back to Board with a project update in Autumn 2023 to confirm the expected start date of April 2024.
7
Any other items
Minutes
Previous Meetings
Join the Discussion
You need to be signed in to comment.
Sign in